Chapter 6 of 7 · How do 20,000 homes act like one power plant?

Virtual Power Plant Field Guide

A gas peaker is one big machine in one place, often 50–100 MW. A virtual power plant is thousands of small machines in thousands of homes: thermostats, water heaters, EV chargers, batteries and solar. Software makes them act as one.

What is a virtual power plant?

A virtual power plant (VPP) is thousands of small devices in people's homes, such as thermostats, water heaters, EV chargers and batteries, run by software so they act like one power plant. When the grid is short of power, they all use a little less, or send a little back, at the same time.

For example, Google announced a deal with Voltus to set up a VPP in the PJM grid. Announced on Oct 22, 2026, the deal adds ~1,070 MW of electric capacity to an earlier 100 MW agreement. That's about the size of a large nuclear reactor, but available only when the grid calls for it!

1

Real hardware, in homes

Every device already exists for another reason: to heat the house, charge the car, back up the lights.

2

Many makers' clouds

Each brand runs its own cloud service: ecobee, Google Nest, ChargePoint, Tesla, Enphase…

3

One aggregator on top

VPP software talks to all those clouds at once and adds the devices up into megawatts.

Watch one event

  1. 1The grid asksThe grid operator needs power from 4 to 8 pm, the same way it would call a power plant.
  2. 2The VPP splits the jobThe aggregator works out how much each kind of device can give, then sends one request to each maker's cloud.
  3. 3Each cloud tells its devicesThermostats shift 2–4°F, EV chargers pause, batteries discharge, water heaters wait. Customers can always override.
  4. 4The grid sees one power plantThe power doesn't travel over the internet. It shows up on the wires the homes already use. The aggregator reports the total.
Common mix-up: ecobee, Nest and Tesla aren't the VPP. They run device clouds. The VPP software (Uplight, EnergyHub, Everyday Electric…) sits on top of them, and the utility's DERMS (chapter 7) checks the wires.
How a VPP works: the grid asks the VPP software for power, the software sends one request to each device maker's cloud, each cloud tells its devices in homes, and the homes' combined change shows up on the feeder as megawatts.

How big is your VPP?

Slide to enroll more homes. The picture above fills in, and the numbers show how much power the fleet gives on a hot evening, how long it lasts, and what it's worth. Picture twenty thousand homes each giving up a small slice of comfort for a few hours.

Your VPP
Want to pick the devices yourself, change the season, or see the rebound?
Starting poweriHow much load the fleet cuts the instant the event starts at 4 pm, when every device responds at once. This is the peak of the event. It fades after that, which is why the tile beside it matters more.
–
at 4 pm, when every device responds
Lowest pointiThe lowest output between 4 and 8 pm. Thermostats fade as houses warm up and batteries run low, so this is the part a grid planner can count on.
–
4 to 8 pm: what you can promise
Customers earniAt Puget Sound Energy's Flex rates: $40 a year per thermostat, $0.50 per kWh for EVs and batteries (batteries capped at $500 a year), 20 events a year. Sign-up bonuses aren't counted.
–
Grid savesiHeld MW × $56 per kW-year: the gap between a new VPP ($43/kW-yr) and a new gas peaker ($99/kW-yr) in the DOE / Brattle 400 MW case (one modeled utility, 2022 dollars).
–
California · Sep 9, 2026
580 MW for 3 hours

From about 140,000 home batteries at the evening peak: roughly 4.1 kW each. A record at the time; a newer dispatch reached 745 MW on Oct 6, 2026 (company-reported).

ecobee · summer 2025
108 MW from 143,000 thermostats

108 MW of load reduction from 143,000 thermostats across 11 events, about 0.75 kW each. California homes averaged about 0.5 kW and Texas about 1 kW.

Puget Sound Energy · Apr 2026
≈49,000 thermostats · 10,800 EVs · 800 batteries

Enrolled in PSE's automated Flex programs (as of Apr 3, 2026): about 49,000 thermostats in Flex Smart and ecobee. Washington law asks PSE to plan for about 500 MW of flexible load by 2030.

How the power numbers are worked out

Each device cuts a little power during the event. Add them all up and you get the fleet's megawatts. Basics and the Playground use the same model. Here it runs for a 95°F summer evening, 4 to 8 pm. (1 kW is a few toasters. 1,000 kW is 1 MW.)

DeviceDevices per 100 homesPower cut per devicePower from 100 homes

  • Thermostat: ecobee's 2025 season, 108 MW ÷ 143,000 thermostats, at 95°F. It fades as homes warm up.
  • Water heater: a typical value, averaged over 4 hours. The tank holds heat, so it can wait.
  • EV charger: a typical value: 7 kW × 60% plugged in × 12% charging at that hour.
  • Home battery: California, Sep 2026, 580 MW ÷ 140,000 batteries. It holds about 3 hours (12 kWh usable).
  • Rooftop solar: no help at 4–8 pm. It filled the batteries at midday.

The mix per 100 homes is a typical one, for illustration, and homes can have several devices. Values marked "typical" are round figures for learning, not engineering numbers.

As of October 2026. Sources: MGRID, Sep 21 2026 · Market Chameleon on ecobee Grid Resiliency, Feb 11 2026

How customer earnings and grid savings are worked out

What a customer earns depends on the program. These are Puget Sound Energy's Flex rates.

DeviceEarns each yearSign-up bonus
Smart thermostat$20 a season, 2 seasons a year = $40$50
Water heaterNot published (PSE pilot)—
EV charger$0.50 per kWh shifted$50
Home battery$0.50 per kWh discharged, up to $500$75 per kWh of battery, up to $1,000
Rooftop solar——

The "Customers earn" tile assumes 20 events a year (PSE allows up to 15 per season) and leaves out sign-up bonuses. Grid saves is the held MW times $56 per kW-year: the gap between a new VPP ($43/kW-yr) and a new gas peaker ($99/kW-yr) in the DOE / Brattle 400 MW case (one modeled utility, 2022 dollars).

As of October 2026. Sources: PSE 2026 Demand Response RFP · pse.com Flex Smart, Flex EV, Flex Batteries · SEIA on DOE VPP Liftoff · Brattle, Real Reliability (2023)

Next →

You're the VPP operator

Fleet: devices enrolled
The call
Real life

Indoor temperature drift

Fleet battery charge

The neighborhood · each house ≈ 500 homes
responding (device color) override offline ↑ rebound
Try these
Pick one to see a lesson, then change one slider at a time.

Per-device values: plan figures as of October 2026, from the California battery record (Sep 2026), ecobee's 2025 season and PSE's Flex programs. Water heater and EV values are typical ones, rounded for learning. A teaching model, not an engineering one.

Going deeper · after the Basics

Inside the VPP box

Chapter 7 drew the VPP as one box. Here it is opened up: four layers, from the grid operator down to the devices in the homes. Click any box.

Mode
telemetry commands bids · forecasts · limits enrollment · meter data · payment 240 V 12 kV feeder

Click a box

Each box tells you what it does, what happens if it fails, and who runs it.

To look like a power plant, a VPP needs…

EnergyHub's "Huels test", Dec 2025. The best VPPs today reach about level 2 of its 0–4 scale.

Events, step by step

Pick a scenario and step through it. Only the boxes and messages involved in each step light up.

VPP glossary

Common mix-ups

Mix-upThe difference

Quiz

Value: who pays, who earns

A VPP is cheap capacity, but only while a program pays for it. Figures as of October 2026.

US VPPs today
30–33 GW
DOE, 2025 update
North America, 2025
37.5 GW
up 13.7% in a year (Wood Mackenzie)
DOE goal for 2030
80–160 GW
10–20% of US peak demand
Worth
≈$10B /yr
in grid savings at that scale (DOE)

VPP vs. gas peaker

Gas peakerVPP
Cost of new capacity$99 /kW-yr$43 /kW-yr
Time to launchseveral years (permits, equipment, interconnection)under 6 months for a basic program (DOE)
Where it sitsone sitethousands of homes
Fuelgasstored energy and shifted load
How long it runsas long as fuel lasts2–4 h, then rebound

Cost: DOE projection for a 400 MW VPP, via SEIA. Brattle (2023) put VPP net cost at about 40–60% of the alternatives. In PJM's 2027–28 auction, demand-side resources were credited at 92% of their MW, up from 69%.

What a customer earns

PSE Flex Batteries: $75 per kWh to sign up (up to $1,000), plus $0.50 per kWh discharged in events (up to $500 a year).

Other programs: PSE Flex Smart pays $50 to sign up plus $20 a season per thermostat. California's DSGS paid Powerwall owners $7–$15 per kW-month in 2026, up to about $280 a year (Tesla).

What's at risk

California's Demand Side Grid Support (DSGS) program paid for the 2025 and 2026 records; the separate Emergency Load Reduction Program (ELRP) joined it for the October one. A VPP depends on a program that pays for it.

  • 2022DSGS starts (California Energy Commission).
  • 2023Home batteries can join. About 700 MW enrolled by 2025.
  • Jul 29, 2025535 MW from 100,000+ batteries, held flat 7–9 pm.
  • Sep 9, 2026580 MW from 140,000+ batteries for 3 hours.
  • Oct 6, 2026745 MW, the current record (company-reported). Called by both DSGS and ELRP.
  • Dec 2026Funding runs out. The final 2026–27 budget added no money for 2027, and a plan to move the program to the CPUC was left out. No successor is funded yet.

Texas: room to grow

ERCOT's ADER pilot lets VPPs sell energy and fast ancillary services. The cap on how much can join has been raised twice as sign-ups filled it.

Launch, Aug 2023
80 MW
First raise
200 MW
Mar 2, 2026
500 MW

Fast ancillary services stay capped at 100 MW across the whole pilot. About 293 MW had qualified by Sep 30, 2026. Base Power, which puts a 25 kWh battery at each home, has a 100 MW deal with CoServ (Mar 2026).

Washington: a winter VPP

Puget Sound Energy peaks on cold mornings and evenings. A 2024 state law asks it to plan flexible load equal to 10% of its peak from 2030.

2021 target for 2025
23.7 MW
Today
129 MW
2030 plan
≈500 MW

PSE 2026 Demand Response RFP (Apr 2026). About 456,000 customers are enrolled by default in Flex event alerts (Apr 2026), a text asking them to cut use; the automated part (thermostats, EVs, batteries) is far smaller but more dependable.

Sources (all accessed October 2026)

National

  1. US DOE, Pathways to Commercial Liftoff: Virtual Power Plants 2025 Update, via Renewable Energy World.
  2. Utility Dive, In 2026, virtual power plants must scale or risk being left behind (Jan 27, 2026).
  3. Utility Dive, Turing test-inspired tool compares virtual power plants to gas peakers (Dec 17, 2025).
  4. Oilprice.com, Virtual Power Plants: The Grid Capacity Nobody Had to Build (2026).
  5. PNNL, FERC Order 2222 DER Policy and Implementation Report (Jan 2026).
  6. SEIA, How virtual power plants are making the grid more affordable.
  7. Brattle Group, Real Reliability: The Value of Virtual Power (May 2023). The $43 vs. $99 per kW-yr comparison is from one modeled utility, in 2022 dollars.
  8. Voltus, Google and Voltus 1 GW virtual power plant in PJM (Oct 22, 2026), and initial 100 MW agreement (Jun 2, 2026).
  9. Facilities Dive, Google–Voltus VPP in PJM (Oct 23, 2026). Secondary source for the ramp-up period and 2040 term.
  10. US DOE, Pathways to Commercial Liftoff: Virtual Power Plants (2025 update, p. 13): net cost of 400 MW of resource adequacy.

California

  1. Latitude Media, Running the numbers on Tesla and Sunrun's massive California VPP test (Aug 2025).
  2. Brattle Group, Assessing VPP Performance (Aug 1, 2025).
  3. MGRID, Sunrun and Tesla push 580 MW from 140,000 home batteries (Sep 21, 2026), and Electrek, same event.
  4. MGRID, California budget threatens DSGS in 2027 (Apr 7, 2026).
  5. Tesla, California DSGS program (2026 payments).
  6. Sunrun, Sunrun and Tesla dispatch 580 megawatts (Sep 21, 2026). Company-reported.
  7. Sunrun, Sunrun leads record grid dispatch (Oct 14, 2026), and Electrek, record 745 MW dispatch (Oct 14, 2026). Company-reported.
  8. Sunrun, Sunrun dispatches a record amount of energy (Aug 4, 2025), citing Brattle.
  9. Canary Media, California guts its biggest virtual power plant (Sep 1, 2026). Secondary source for the 2027 DSGS budget.
  10. California Energy Commission, DSGS Program Guidelines, 5th ed. (Apr 2026).

Texas

  1. ERCOT, ADER Pilot Project, and Market Notice M-A030226-01 (Mar 2, 2026).
  2. Utility Dive, 2 Tesla virtual power plants cleared to provide energy to Texas grid (Aug 24, 2023).
  3. Energy-Storage.news, Base Power launches 100 MW VPP programme in Texas (Mar 10, 2026).
  4. ERCOT, ADER update to the Texas Senate Business and Commerce Committee (Sep 30, 2026): 293 MW qualified.
  5. ERCOT, ADER Phase 4, Wholesale Market Subcommittee (Oct 7, 2026).
  6. Base Power, Aggregated DERs and the capacity crunch (Aug 2026). Company source.

Washington

  1. Puget Sound Energy, 2026 Demand Response RFP (Apr 2026).
  2. Puget Sound Energy, Flex Batteries, Flex Smart and Flex EV.
  3. MyNorthwest, January flex event affects 260,000 PSE customers (Jan 12, 2024).
  4. KIRO 7, PSE Flex program faces first real test as heat hits Puget Sound (Jul 21, 2026). Its 640,000 enrollment figure was not confirmed against PSE's filings.
  5. Puget Sound Energy, 2026 Demand Response RFP, as filed with the Washington UTC (Docket UE-260005): program enrollments as of Apr 3, 2026.
  6. Washington Legislature, ESHB 1589 (Laws of 2024, ch. 351), and WAC 480-96-050: demand response of at least 10% of peak from 2030. The ≈500 MW figure is PSE's own estimate.
  7. Puget Sound Energy, 2025 Demand Response Equity Action Plan.

Devices and platforms

  1. ecobee, Grid Resiliency service unlocks 2.8 GW of capacity (Feb 10, 2026), and Demand Side Analytics, ecobee Grid Resiliency evaluation: 143,000 devices, 11 events, 108 MW.
  2. Market Chameleon, ecobee Grid Resiliency (Feb 11, 2026): 143,000 thermostats, 108 MW. Secondary source.
  3. Bonneville Power Administration CTA-2045 water heater results, ACEEE Hot Water Forum (2019), and the Regional Technical Forum, residential hot water heater demand response.
  4. Eversource off-peak EV charging evaluation, NH PUC Docket 20-170 (2023), and East Kentucky Power Cooperative, KY PSC Case 2026-00163 (Aug 2026): measured EV load shift of about 0.2–0.25 kW per car.
  5. Utility Dive, Renew Home becomes Everyday Electric (Oct 7, 2026).
  6. EnergyHub, First to exceed 1 million devices under management (2024).
  7. Renewable Energy World, Uplight to acquire AutoGrid (2024).