Demand is growing, so the grid needs new power plants. Every one of them has to get in line first: before a plant can connect to the transmission grid, it files a request and waits while the grid operator studies it. The grid operator is the organization that runs the transmission grid in a region, such as ERCOT in Texas or PJM in the mid-Atlantic. In some places a utility does that job instead. It studies each request to see what the new plant would do to the grid and what would have to be built to take it. Grid operations covers what these organizations do all day. Those lines, called interconnection queues, are public. Imagine you're buying power for a utility or a data center. The queue is your shopping list. Here's what's on it, and how much of it you can count on. Reading it is like reading a waiting-room roster: many of the names will leave before they are called.
Point of interconnection (POI) is the exact spot, usually at a substation, where a new plant plugs into the grid.
Substation is a fenced yard of transformers and switches where power lines meet and voltage steps up or down.
Network upgrades are the lines, transformers and breakers the grid has to add or replace so the new plant doesn't overload what's there. The developer often pays some or all of the cost, and the rules vary by region.
ISO / RTO is an independent system operator or regional transmission organization. This is the nonprofit that runs the grid and the wholesale power market for a region, such as ERCOT, PJM, MISO or CAISO. Outside these regions, such as the Southeast and much of the West, individual utilities run the queue.
Active requests at the end of 2025, by region. Click a region (or use the Region menu) to follow it through the page.
Requests placed on the map in the year they entered the queue. Choose which ones to show: everything ever requested, only those still waiting today (what the map above shows), or those that were withdrawn. Two views are about projects that were built: Built (by request year) places them in the year they were requested, and Came online places them in the year they began operating. Press play to watch where projects were proposed and how the mix of types changed. The Region and Measure menus above apply here too.
Each bubble is a county; its size is the requested there and its color is the type with the most. The bubble scale is the same in every year, so years can be compared.
A hybrid is a solar plant built with a battery on the same site and the same grid connection (how batteries work). Many grid operators list a solar-plus-battery plant as one request and don't give the battery's size: 1,389 of the 1,716 active solar + battery requests in the data file list no battery size. Berkeley Lab fills the gaps with an estimate, using the battery-to-solar ratio from hybrids that do list both (Queued Up 2026, slides 8, 16 and 30), and includes it in the report's headline totals. The published project data leaves those estimates out, so every chart built from it, including the rest of this page, understates storage and solar + storage. The report doesn't publish the ratios. The estimated part is about 197 GW of the 2,061 GW. CAISO lists almost every hybrid's battery, so it needs little estimating. For ERCOT the report's total (408 GW) equals the project rows, so no estimate was added there, and the data file lists no separate battery size for ERCOT's hybrids. ⚠ Whether those rows hold the solar size or the whole plant is not stated; to confirm with Berkeley Lab.
ERIS (Energy Resource Interconnection Service) is the basic level. The plant can connect and sell its energy when there is spare room on the transmission lines. If the lines get crowded, it may have to cut back. It needs fewer grid upgrades, so it is usually cheaper and quicker.
NRIS (Network Resource Interconnection Service) is the full level. The grid operator studies the plant as if it were one of the utility's own, able to deliver its full output to customers across the network, so it can count toward reliable-capacity needs. It usually needs more grid upgrades, so it costs more and takes longer.
A rough comparison: ERIS is a standby ticket, and NRIS is a reserved seat. Rules and names differ between grid operators, and some requests list both or neither. You can see each project's service level in the project list (click a county on a map).
Every request by the year it entered the queue, whatever happened to it later. Bar height is what was asked for, not what was built. Storage and solar + storage are understated †.
Status at the end of 2025, by the year each request entered. Requests from 2021 on are too young to judge: with a 5-year lead time, most haven't had time to finish.
Source. Rand et al., Queued Up: 2026 Edition data file (Lawrence Berkeley National Laboratory with Interconnection.fyi, May 2026), data through the end of 2025. Tab 3 lists every request (38,201 generation and storage requests). Tab 10 has the report's totals of active capacity by region, and its installed capacity by type for 2025, which adds up to the 1,374 GW U.S. power plant fleet we compare the queue with. Tab 21 has EIA's count of new transmission-connected capacity.
Capacity. A project's size is the sum of its listed parts (MW 1–3). A hybrid's battery counts only where the queue gives its size, so the project rows understate storage (note † in section 1). The headline figures, including 2,061 GW, are the report's own and include Berkeley Lab's estimates for missing battery sizes. The table in section 1 shows the steps from the headline to the charts: 2,061.3 GW, minus 196.5 estimated hybrid batteries, is 1,864.8 GW in the project rows; minus 5.6 with no request date is 1,859.2 GW in the by-year charts.
Types. Each project is counted once. Solar; Solar + storage (solar with a battery); Storage (batteries and other storage); Wind (onshore, offshore, and wind with a battery); Gas (including gas combined with batteries, oil or other fuels); Other is everything else: hydro, nuclear, coal, geothermal, oil and diesel, hydrogen, and mixes of several resources such as solar + wind + battery.
Status. Still waiting is an active request. Built is an operating project. Withdrawn and suspended are as listed (suspended is about 2% of requests). Ten requests with an unknown status are left out of the charts.
Years. The request year is the year a request entered the queue. 665 requests have no request date, so they count in totals but not in by-year charts or the year-by-year map. Came online is the year of a project's in-service date; the chart in section 3 uses only those dates. On the year-by-year map, a built project with no in-service date is placed by its proposed online date instead (964 projects). The two dates fall in the same year for about 77% of the projects that have both, and within a year for 88%. Built projects with neither date (436) are not shown there.
Headline facts. Gets built is the share of capacity requested in 2000–2020 that was operating by the end of 2025 (12.8%, shown as 13%). It uses status, not dates, because some regions are missing many withdrawal dates (ERCOT about 51%). Request to operation is the median time between a project's request date and its in-service date, for projects that came online in 2024 (61 months; 56 for 2023 and 65 for 2025).
Maps. Each bubble sits at the center of a county, using the county listed for the request. 1,770 requests list no county (about 1% of active capacity), and Alaska, Hawaii and the territories are not drawn, so those are not on the maps. Region shading is approximate, not official ISO boundaries: each county takes the grid region with the most requests in it, and counties with none take their neighbors' majority. The main map shows still-waiting requests only. The year-by-year map shows requests of any status unless you filter, draws bubbles at the same scale in every year, and leaves out requests with no county or request date (about 6%). Clicking a bubble lists the county's projects from the data file. Queue IDs repeat across utilities, so each project also shows its row number in the Excel file.
EIA line. The line in section 3 is EIA's count of new transmission-connected plants in the same regions, not every plant.
Open questions. The report's text counts 8,244 active projects; the data file lists 8,513, and we have not reconciled the two. For ERCOT the report's total equals the project rows, so no hybrid-battery estimate was added, and it is not stated whether ERCOT's hybrid rows hold the solar size or the whole plant.