A hands-on look at how Distributed Energy Resources (DERs) — solar, batteries, and the equipment that connects them — interconnect with the distribution grid. Worked example: a municipal site with 250 kW AC solar + 750 kW AC battery storage (an even 1,000 kW total DER nameplate). Using the rule of thumb that 1 MW ≈ 500 average homes' worth of instantaneous demand, that's roughly 500 households' worth of capacity tying into one feeder.
Adjust solar, load, and the battery — then flip the grid outage switch and watch what the DER Gateway actually does. This uses real interconnection logic, not just a visual toggle.
Two separate cost buckets: what the utility installs on its side of the meter to accept the DER safely, and what the customer/developer installs on-site to generate and store the power. Figures are illustrative planning-level ranges, not a bid.
| Equipment | Role | Approx. cost |
|---|---|---|
| 1 MVA distribution transformer | Steps feeder voltage down to service voltage sized for the combined 1,000 kW DER + site load | $100,000 |
| Pole-mounted recloser | Utility-side fault protection; isolates the DER's tap point from the rest of the feeder during a fault | $70,000 |
| DER Gateway / interconnection meter & comms | Utility visibility & control point — monitors export, can signal curtailment or trip | $3,000 |
| Utility-side subtotal | $173,000 | |
| Equipment | Typical unit cost | This site | Approx. cost |
|---|---|---|---|
| PV array + racking + string inverters (250 kW AC) | ~$1.50–$2.20/W AC | 250,000 W | $375,000–$550,000 |
| BESS — battery, PCS/inverter, enclosure, HVAC, fire suppression (750 kW / ~1,500 kWh, 2-hr duration) | ~$350–$500/kWh | 1,500,000 Wh | $525,000–$750,000 |
| Microgrid controller + automatic transfer switch (optional — only needed for intentional islanding) | flat | — | $150,000–$400,000 |
| Customer-side subtotal (with islanding) | ≈ $1.05M–$1.70M | ||