Chapter 3 of 4 · What changes when a customer makes power too?

DER & Microgrid Field Guide

A hands-on look at how Distributed Energy Resources (DERs) — solar, batteries, and the equipment that connects them — interconnect with the distribution grid. Worked example: a municipal site with 250 kW AC solar + 750 kW AC battery storage (an even 1,000 kW total DER nameplate). Using the rule of thumb that 1 MW ≈ 500 average homes' worth of instantaneous demand, that's roughly 500 households' worth of capacity tying into one feeder.

Site One-Line: Grid ↔ DER Interconnection

Utility primary (~12 kV) Secondary (site voltage) DC side of an inverter Data + control Who owns it Solar · battery swatch
Click any piece of equipment for a plain-language explanation.
Select a component above to see what it does, who owns it, and roughly what it costs.

DER & Microgrid Glossary

Power-Flow Playground

Adjust solar, load, and the battery — then flip the grid outage switch and watch what the DER Gateway actually does. This uses real interconnection logic, not just a visual toggle.

Adjust the controls to begin.
Max available: 750 kW discharge · 0 kW charge
Grid status

Planning-Level Costs — 1,000 kW DER Interconnection Example

Two separate cost buckets: what the utility installs on its side of the meter to accept the DER safely, and what the customer/developer installs on-site to generate and store the power. Figures are illustrative planning-level ranges, not a bid.

Utility-side interconnection equipment Utility owned

EquipmentRoleApprox. cost
1 MVA distribution transformerSteps feeder voltage down to service voltage sized for the combined 1,000 kW DER + site load$100,000
Pole-mounted recloserUtility-side fault protection; isolates the DER's tap point from the rest of the feeder during a fault$70,000
DER Gateway / interconnection meter & commsUtility visibility & control point — monitors export, can signal curtailment or trip$3,000
Utility-side subtotal$173,000

Customer-side DER equipment Customer / developer owned

EquipmentTypical unit costThis siteApprox. cost
PV array + racking + string inverters (250 kW AC)~$1.50–$2.20/W AC250,000 W$375,000–$550,000
BESS — battery, PCS/inverter, enclosure, HVAC, fire suppression (750 kW / ~1,500 kWh, 2-hr duration)~$350–$500/kWh1,500,000 Wh$525,000–$750,000
Microgrid controller + automatic transfer switch (optional — only needed for intentional islanding)flat—$150,000–$400,000
Customer-side subtotal (with islanding)≈ $1.05M–$1.70M
Ranges are planning-level and vary heavily by region, labor rates, site conditions, interconnection study results, and whether islanding capability is included. The utility-side figures come from a real interconnection cost estimate for this exact 1,000 kW example; the customer-side figures are broad industry ranges (NREL/EIA cost benchmarks) meant to show relative scale, not a quote. Note the utility equipment ($173K) is a small fraction of total project cost — its purpose isn't to handle bulk power, it's to make the DER safe and visible to the grid.

Quiz